Santas Solar Power Plant

Client: Akuo Renewables

  • Land Suitability Study
  • Preliminary layout and production estimate
  • Constraints and restrictions analysis
  • Topography
  • Licensing projects
  • Environmental Impact Study
  • Contacts with relevant entities
  • Preparation of licence applications
  • Overall coordination of the process

Area
356 ha

Power
150 MVA

MVL

30kV – 1.3km

VHVL

400kV – 4.9km

Technical Due Dilligences

Client: Multiple - Confidential

  • Documental evaluation (Data Room)
  • Risk Matrix / Red Flags
  • Yield Production
  • PVsyst model
  • Full report

Margalha Solar Power Plant

Client: Akuo Renewables

  • Land Suitability Study
  • Preliminary layout and production estimate
  • Constraints and restrictions analysis
  • Topography
  • Licensing projects
  • Environmental Impact Study
  • Contacts with relevant entities
  • Preparation of licence applications
  • Overall coordination of the process

Area
330 ha

Power
120 MVA

VHVL
400kV – 21km

Hydrogen Production Unit

Client: RegaEnergy

  • Technical feasibility studies
  • Environmental feasibility studies
  • Licensing feasibility studies

Polvorão Solar Power Plant

Client: Akuo Renewables

  • Land Suitability Study
  • Preliminary layout and production estimate
  • Constraints and restrictions analysis
  • Topography
  • Licensing projects
  • Environmental Impact Study
  • Contacts with relevant entities
  • Preparation of licence applications
  • Overall coordination of the process

Area
286 ha

Power
100 MVA

VHVL

400kV – 13km

MVL

30kV – 1.3km

Carregado Solar Power Plant

Client: ENFINITY

  • Land Suitability Study
  • Preliminary layout and production estimate
  • Constraints and restrictions analysis
  • Licensing projects
  • Overall coordination of the process

Area
132 ha

Power
50 MVA

VHVL

220kV – 7.7km

Photovoltaic Park
Solar da Luz

Client: Audax

  • Land Suitability Study
  • Preliminary layout and production estimate
  • Constraints and restrictions analysis
  • Topography
  • Licensing projects
  • Environmental Impact Study
  • Contacts with relevant entities
  • Preparation of licence applications
  • Overall coordination of the process

Area

241 ha

Power
99 MVA

VHVL

400kV – 15km

Orada Solar Power Plant

Client: Akuo Renewables

  • Land Suitability Study
  • Preliminary layout and production estimate
  • Constraints and restrictions analysis
  • Topography
  • Licensing projects
  • Environmental Impact Study
  • Contacts with relevant entities
  • Preparation of licence applications
  • Overall coordination of the process

Area
140 ha

Power
30 MW

VHVL

30kV – 2,7km

Very High Voltage Line
Torre Bela

Client: NEOEN / Aura Power

  • Study of major constraints
  • Environmental Impact Study

Malveira Self-consumption unit

Client: Queijos Santiago

  • Layout and production estimate
  • Constraints and restrictions analysis
  • Electrical project
  • Licensing
  • Implementation
  • Contacts with relevant entities
  • Overall coordination of the process
Area 2785 sqm

Power
580kW

Produced Energy

879,3 MWh/year

No. Panels

1066

Environmental Due Dilligences

Client: Multiple - Confidential

  • Documental evaluation (Data Room)
  • Identification and evaluation of constraints
  • Cartography
  • Risk assessment
  • Red flags
  • Mitigation measures

Self-consumption Unit

Client: SOMINCOR

  • Land Suitability Study
  • Preliminary layout and production estimate
  • Constraints and restrictions analysis
  • Licensing projects
  • Contacts with relevant entities
  • Preparation of licence applications
  • Overall coordination of the process

Area
115 ha

Power
49MW

Portalegre Self-consumption Unit

Client: Queijos Santiago

  • Layout and production estimate
  • Constraints and restrictions analysis
  • Electrical project
  • Licensing
  • Implementation
  • Contacts with relevant entities
  • Overall coordination of the process

Area
3193 sqm

Power
666kW

Produced Energy

987,2 MWh/year

No. Panels

1222

Hydrogen Production Unit

Client: Smartenergy

  • Environmental Studies

Lapa Self-consumption Unit

Client: Queijos Santiago

  • Land Suitability Study
  • Preliminary layout and production estimate
  • Constraints and restrictions analysis
  • Licensing projects
  • Contacts with relevant entities
  • Preparation of licence applications
  • Overall coordination of the process

Area
418 sqm

Power
87,2kW

Produced Energy

132 MWh/year

No. Panels

160

Solar Park of
Sta. Clara de Louredo

Client: Akuo Renewables

  • Land Suitability Study
  • Preliminary layout and production estimate
  • Constraints and restrictions analysis
  • Topography
  • Licensing projects
  • Environmental Impact Study
  • Contacts with relevant entities
  • Preparation of licence applications
  • Overall coordination of the process

Area
313,5 ha

Power
240 MVA

VHVL

400kV – 15km

Photovoltaic Park
Solar do Céu

Client: Audax

  • Land Suitability Study
  • Preliminary layout and production estimate
  • Constraints and restrictions analysis
  • Topography
  • Licensing projects
  • Environmental Impact Study
  • Contacts with relevant entities
  • Preparation of licence applications
  • Overall coordination of the process

Area

123 ha

Power
58 MVA

VHVL

400kV – 15km

Comenda Solar Power Plant

Client: Akuo Renewables

  • Land Suitability Study
  • Preliminary layout and production estimate
  • Constraints and restrictions analysis
  • Licensing projects
  • Contacts with relevant entities
  • Preparation of licence applications
  • Overall coordination of the process

Area
140 ha

Power
20 MW

VHVL

30kV – 7,5km

Get in touch with Átomo